Overview
Master project planning for the PE Civil exam including CPM scheduling, earned value management, cost estimation, and activity network diagrams.
This topic accounts for 4 out of 40 questions on the PE Civil Civil Breadth (AM) exam.
Key Concepts
Critical Path Method (CPM)
CPM identifies the longest sequence of dependent activities that determines the minimum project duration. The critical path has zero total float. To find it: (1) Forward pass to calculate Early Start (ES) and Early Finish (EF), (2) Backward pass to calculate Late Start (LS) and Late Finish (LF), (3) Total Float = LS - ES = LF - EF. Activities with TF = 0 are on the critical path.
Earned Value Management (EVM)
EVM integrates scope, schedule, and cost to measure project performance. Key metrics: PV (Planned Value) = budgeted cost of scheduled work, EV (Earned Value) = budgeted cost of completed work, AC (Actual Cost) = actual cost of completed work. CPI = EV/AC (cost efficiency), SPI = EV/PV (schedule efficiency). CPI < 1 means over budget; SPI < 1 means behind schedule. EAC = BAC/CPI estimates final cost.
PERT Estimation
Program Evaluation and Review Technique uses three time estimates for each activity: Optimistic (O), Most Likely (M), and Pessimistic (P). Expected time = (O + 4M + P)/6. Standard deviation = (P - O)/6. Variance = [(P - O)/6]^2. The variance of the critical path equals the sum of variances of critical activities.
Quantity Takeoff and Cost Estimation
Cost estimation methods include: Analogous (top-down using historical data), Parametric (statistical models), Bottom-up (detailed quantity takeoff). For earthwork: Average End Area method V = L(A1+A2)/2 converted to cubic yards by dividing by 27. For concrete: calculate volume in cubic yards. Material costs = quantity x unit price + waste factor (typically 5-10%).
Common Exam Question Types
- Calculate total float for an activity in a network diagram
- Determine the critical path and project duration
- Calculate EVM metrics (CPI, SPI, EAC, ETC)
- Estimate activity duration using PERT
- Compute earthwork volumes from cross-sections
Exam Tips & Strategies
Practice This Topic
Test your knowledge with free practice problems
Practice Problems Browse Equations