Project Planning Study Guide

PE Civil Breadth (AM) Exam Preparation

4 Exam Questions Civil Breadth (AM)

Overview

Master project planning for the PE Civil exam including CPM scheduling, earned value management, cost estimation, and activity network diagrams.

This topic accounts for 4 out of 40 questions on the PE Civil Civil Breadth (AM) exam.

Key Concepts

Critical Path Method (CPM)

CPM identifies the longest sequence of dependent activities that determines the minimum project duration. The critical path has zero total float. To find it: (1) Forward pass to calculate Early Start (ES) and Early Finish (EF), (2) Backward pass to calculate Late Start (LS) and Late Finish (LF), (3) Total Float = LS - ES = LF - EF. Activities with TF = 0 are on the critical path.

Earned Value Management (EVM)

EVM integrates scope, schedule, and cost to measure project performance. Key metrics: PV (Planned Value) = budgeted cost of scheduled work, EV (Earned Value) = budgeted cost of completed work, AC (Actual Cost) = actual cost of completed work. CPI = EV/AC (cost efficiency), SPI = EV/PV (schedule efficiency). CPI < 1 means over budget; SPI < 1 means behind schedule. EAC = BAC/CPI estimates final cost.

PERT Estimation

Program Evaluation and Review Technique uses three time estimates for each activity: Optimistic (O), Most Likely (M), and Pessimistic (P). Expected time = (O + 4M + P)/6. Standard deviation = (P - O)/6. Variance = [(P - O)/6]^2. The variance of the critical path equals the sum of variances of critical activities.

Quantity Takeoff and Cost Estimation

Cost estimation methods include: Analogous (top-down using historical data), Parametric (statistical models), Bottom-up (detailed quantity takeoff). For earthwork: Average End Area method V = L(A1+A2)/2 converted to cubic yards by dividing by 27. For concrete: calculate volume in cubic yards. Material costs = quantity x unit price + waste factor (typically 5-10%).

Common Exam Question Types

Exam Tips & Strategies

For CPM problems, always do the forward pass first (ES, EF), then backward pass (LS, LF)
Remember: CPI = EV/AC, SPI = EV/PV. Both should be > 1 for good performance
EAC = BAC/CPI is the most commonly tested EVM formula
Total Float = 0 defines the critical path. Free Float only affects the immediate successor

Practice This Topic

Test your knowledge with free practice problems

Practice Problems Browse Equations

Related Study Guides